Project: Temporary 2,000 Ton Cooling Tower System
Solution: Create portable cooling tower system by utilizing a gravity feed system.
CRS installed a standby system of 2000 tons in case of a failure with the customers existing tower system.
The towers supplied by CRS had to be installed at an elevation higher than the existing cooling tower system to facilitate a gravity feed from the temporary tower to the permanent tower water system.
CRS used steel pipe with victaulic fittings to put the system together.
![]() |
![]() |
![]() |